ROAD CONSTRUCTION NOTICE

Capital Improvement Program Roadway Repair Project- Shepherds Glen

PROJECT SCOPE:  The City project includes reconstruction of the intersection of Shepherds Glen Road and Stillwaters.

  • The construction is scheduled to begin at on Monday, April 13, 2015 (weather permitting).
  • Construction is allowed between 7:00 am to 8:00 pm, Monday through Friday.
  • The roadway will typically be constructed one-half at a time and will be reduced to one lane during construction.
  • Access to homes will be maintained during construction. Driveways within the pavement repair area may not be accessible when the driveway approaches are being re-constructed. The contractor will notify the homeowner in advance.
  • The contractor’s estimated completion time is 14 calendar days (weather permitting).

The contractor is Estrada Concrete Company, 469-279-3464.

If you have any questions or concerns regarding the referenced project, please contact Jeff McKenzie at the City of Heath Public Work’s Office: 972-961-4899 or at his email: jmckenzie@heathtx.com.