HUBBARD BRIDGE PROJECT UPDATE

UPDATE: 07/14/23 Main lane of Hubbard Drive concrete has been poured. Expansion joints will be cleaned and sealed on Saturday July 14, 2023. Guardrail is scheduled to be delivered on Friday July 14, 2023 and installation will begin. Nighttime installation has been approved due to the daytime heat. Back filling of curbs is complete. Transitions […]

Rabbit Ridge Phase 2 Project: Roadway Closed to Through Traffic beginning February 14

Road Closure Benefits: Limiting traffic to local homeowners during the remainder of the project will enable Ed Bell Construction to dramatically reduce the remaining time to complete the project.

WATER CONSERVATION EMERGENCY ALERT

The City of Heath has been notified by the City of Rockwall that water supply to the City of Heath will be stopped for a 20-hour period starting at 7:00 am, Thursday January 26th, 2023 and running to the early morning hours of Friday January 27th. This curtailment of flow from the City of Rockwall […]

CONSTRUCTION UPDATE: STANFORD COURT AND FM 740 ENTRANCE

PROJECT SCOPE: Concrete paving will be repaired at the entry into Highlands of Heath at FM 740 and Stanford. Four full panels will be replaced. This will require the full closure of the entry on December 19 beginning at 8 a.m. through December 21. Traffic may enter and exit the Highlands of Heath neighborhood at […]

CONSTRUCTION NOTICE: ANTIGUA BAY WATER LINE UPGRADE

Please be advised that on Tuesday, 11/01/22 the main water supply to the Antigua Bay neighborhood will temporarily be out of service, from 9:00 A.M. until 3:00 P.M. due to improvements to the public water system. Thank you for your cooperation, we will keep inconveniences to a minimum. If you have any questions or concerns, […]

City to Host Town Hall Meeting on September 1 Regarding Hubbard Bridge Closure

The City of Heath will host a Town Hall Meeting regarding the Hubbard Bridge closure on Thursday, September 1 at 6 p.m. at City Hall. The bridge was closed for safety reasons due to erosion and damage caused during the heavy rain incident last week. The detour route is shown below. Topics to be discussed […]

CONSTRUCTION NOTICE: RABBIT RIDGE PHASE 2 CONSTRUCTION

PROJECT INFORMATION: The second phase of Rabbit Ridge Paving Improvements is set to begin on June 23, 2022. Time of construction is 270 calendar days with a completion date in March of 2023. The improvements include a new 12-inch water line along the west ROW of the roadway and two new lanes of concrete. The […]

CONSTRUCTION NOTICE: HUBBARD DRIVE LAKE CROSSING REPAIRS (UPDATED 04/19/22)

PROJECT SCOPE: The City of Heath has hired a contractor to construct temporary repairs to the embankment area that eroded and settled last year. The Contractor has made good progress the first two days of construction and if weather permits hopes to begin placing concrete later this week. Working conditions are tight and visibility is […]

CONSTRUCTION NOTICE: COVE RIDGE WATERLINE UPGRADE PROJECT

PROJECT SCOPE: The City of Heath has hired a contractor to upgrade waterlines in the Cove Ridge Subdivision. The waterline upgrade project is the replacement of the existing old water lines with new 8-inch and 6-inch water lines and installing additional fire hydrants. The waterline installation will be constructed to minimize impact to the traffic […]

CONSTRUCTION NOTICE: AUTUMN TRAIL WATER LINE EXTENSION PROJECT

PROJECT SCOPE: A contractor is extending the water line in Autumn Trail. In order to install the water line extension, the water within the Candlelite Subdivision will need to be shut off two different days for 6 hours each day. The waterline installation is being constructed to minimize impact to the City water customers. The […]

CONSTRUCTION NOTICE: ANTIGUA BAY WATERLINE UPGRADES- PHASE 1 PROJECT

PROJECT SCOPE: The City waterline upgrade project is the replacement of the existing small water lines with new 6-inch water lines and fire hydrants within the Antigua Bay Subdivision. This project is the first of two phases. The exhibit below is Phase 1. Phase 2 is scheduled for later in 2022. The waterline installation will […]

2020-2021 Annual Concrete Roadway Repair Project

PROJECT SCOPE: The City concrete roadway repair project is the replacement of concrete pavement at various locations throughout the City, including repair of several sections of Heathland Crossing between FM-740 and White Road. The work on Phase 1 of the Heathland Crossing repair is complete. Phase 2, eastbound Heathland Crossing from the end of Phase […]